Category Archives: tech

The Reasons Projects and Programmes Fail

In this post I’ll be describing the five categories that I’ve identified of reasons that Projects and Programmes Fail, this categorisation has been built up from doing a large number of system, project and programme reviews and audits over the years, and this article follows on from the project review and programme audit framework which I wrote about recently.

Whatever problems are found in a project or programme in my experience they can be broken down into these five categories:

  1. Strategic / Alignment
  2. Contractual / Financial
  3. People / Politics
  4. Process / Procedural
  5. Technical / Architectural

For a number of years my categorization of reasons why projects and programmes fail did not include “Strategic / Alignment” as an area, and was a model made up of just the other four categories, but then I kept coming across a couple of definitive reasons why it should be added; more on this below.

So lets look at these five categories individually in more detail:

    1. Strategic / AlignmentA fundamental lack of strategic alignment to the Business has been made.

      Basically the project should never have been commissioned in the first place. It is either not required whatsoever (and yes, shockingly, I have come across this happening), or is no longer required (either because of a change of business circumstance, or functionality overlap with another system, i.e. something else does this just fine thank you very much).

      A lack of an Executive Sponsor is a good indication that this could be an issue, and even if the project or programme is some form of ‘Skunk Works’ you would expect the overall ‘Skunk Works’ innovation concept and framework to be supported by an Executive Sponsor, such as the Head of R&D;, and for a watching brief kept over costs versus potential revenues and benefits.

      Projects and programmes which are purely or highly non-functional, and provide limited, or unperceived business benefit, may also be an indication of this issue.

    1. People / PoliticsGetting people to work together can be complex and difficult, especially when their goals are not co-ordinated. Long term political enemies, people competing for resources, promotions and remuneration, are all potential issues.

      This magnifies up at a macro level into business units being in competition for talent, resources and even access to customers and partners. Programmes where multiple business units have to work together and integrate systems and functionality are almost always problematic, even when there are serious penalties if it not done.

      In general Governance compliance issues and management failings also fall into this category, as do business conduct issues, moral, etc.

    1. Process / ProceduralThe process is ‘broken’. Procedures are not in place or are not being complied with. It is either the wrong process to have been used in the first place, is not being adhered to correctly, or is not even being used at all.

      A process is in place but it is over subscribed and can not ‘scale’, alternately a process does not have enough people to service it, perhaps because of downsizing or such.

      The status of a capable Project Management Office (PMO), or of stable, authoritative, Document Repository are also indicators that there is a problem in this area, as is a lack of due diligence when managing and implementing change control.

      Governance in terms of appropriate operating model and related procedural items are here too.

    1. Contractual / FinancialFor some reason the financial arrangements of the project are having a negative impact on the ability to deliver that project. The contract is counter intuitive perhaps, or is weighted in such a way that means that the ends are not easily achieved, or does a poor job of defining the requirements.

      If you hear something like the “spirit of the contract” versus the “word of the contract” then this is a good indicator that there is an issue with the contract and that it doesn’t cover what is wanted or expected.

      Be aware that this is likely to be a problem shared by the client and their vendors as mutual understanding of what can be delivered versus what is wanted and needed by the business. This a re-iterative learning process as the business learns more about what can be delivered by technology and the system defined, whilst those involved in delivery learn the semantics, language and nature of the business and experience more of the challenges that the business has.

  1. Technical / ArchitecturalThis is last for a very good reason, and that is this is often the least contributing factor in terms of projects failing to deliver.

    When there are issues in this area in my experience it is often one of not having the appropriate people and skills at the right time, or not even identifying the key individuals you require accurately, rather than hard technology issues.

    Other issues are architectural and compositional problems (more on architectural issues in an upcoming article), access to resources at the right time, and the typical technology compatibility issues (i.e. “what works with what”) and access to vendor technology and knowledge bases.

    As a reviewer of projects and programmes which could be failing it’s likely that you will have come from a technology implementation background and that this area is well within your ‘comfort zone’, but I assure you that in the majority of cases technology may well be a minor contributing factor to the failure of an overall project, nor is the hardest problem area to improve upon (with good recommendations, of course), but it may be an area that you could potentially over focus upon and lose sight of more significant issues at hand.

Again, hope you enjoyed the article, will try and look at some other pieces, such as the top architectural mistakes made, how to identify possibly failing projects and suggestions for rescuing them.

Project Review and Programme Audit Framework – a simple example of it’s use

This is a simple example review utilising the project review and programme audit framework that I wrote about in the proceeding article. …..

Project Review and Programme Audit Framework

So this is the framework I have developed and use for reviewing and auditing failing projects, programmes and systems. As I might have said before this is a simple, effective, framework, based on my experience, and although you might have seen approaches like this before, this is one that I have personally used to great effect.

To an extent this framework is a description of how I document a review and the process steps that I take as well, the major difference is that the process itself is likely to be re-iterative and you well learn things during the review which generate fresh lines of inquiry.

I get asked to perform these types of review probably because I’ve done a large number of them and have become quite good at them, however originally I think it was because I have an analytical and inquiring mind, I am tenacious enough to chase down what is really happening in a situation, have a broad and deep appreciation of technology and it’s implementation, I have a great deal of project and programme experience across a number of Industry’s, and am good at getting people to tell me about the problems they are experiencing. I expect these are the type of qualities you would probably want to encourage to become better at this type of activity; an unkind person might say that being a pedant and didact can help too.

So I separate my reviews down into five simple areas:

  1. Problem(s)
  2. Fact(s)
  3. Result(s)
  4. Conclusion(s)
  5. Recommendation(s)

I bet you’re thinking “well that’s obvious Wayne”, but simplicity is always an imperative when you set out, because believe me, the complexity of the issues you’re going to find can sometimes seem overwhelming. So explaining what I mean by these five headings:

  1. Problem(s)Or rather perceived problem(s). Because this is what the client thinks is wrong or at the very least is the effect not the cause (unless they know or think they know what the problem is and just want an expert to confirm their opinions). If in doubt this should definitely be why you have been commissioned.

    This section should not really be that large, because otherwise I would expect that items from the following sections have ‘leaked’ into here, most likely from the ‘fact(s)’ section. For instance if the MD of a company who has commissioned you to review a system starts telling you about all the individual issues that they are having then you are clearly in ‘gathering facts’ mode and much of this should end up in the next section.

    I would typically expect this section to be only a paragraph or couple of paragraphs at the most, if it’s running to half a page or more I’d be concerned because in a large review clarity will matter a great deal. Even in a large scale, complex review, be careful of this section because if it is too large it could point to being too over-focused on detail which should be drawn out further in the review or a problem with the level of abstraction used and the problem description.

    Examples of ‘Problems’ I’ve been asked to investigate include:

    • We’ve spent £10s of Millions on our IT supplier and the web sites which they have built are still not available when they are needed to be, what is going wrong
    • We’ve spent £30 Million plus to date on a data centre build out, which should be complete, and our IT supplier keeps telling us that it could be a month or a couple of months until it’s complete, but we have lost confidence in their updates.
    • We have spent over £70 Million on a large integration project, which has yet to deliver it’s first release to the business and I’ve just been told it’s going to need another £10 Million immediately and another £40 Million to complete
    • We are just under two years into a ten year, £300 Million pound a year contract, which has ‘ballooned’ up to £800 Million per year already, and yet our supplier still hasn’t delivered the ‘Transformation’ that they promised, what is stopping them
  2. Fact(s)Gather and document facts. This should easily be your largest section because data matters and you will need good data to make an appropriate diagnosis of the situation and to ensure you deliver a credible and believable review.

    Obviously there are many ways to gather data, especially technically i.e. gather crash dumps, read through code, measure network, processing and storage performance and capabilities, etc. For non-technical fact gathering you can review contracts, documentation, investigate online and offline document repositories, review authorised and freely given email and communication trails and other ‘digital echos’ as you see is appropriate, etc.

    By far the most effective means of gathering facts in a large scale and complex review is via interviews. In a large scale review you would expect to find the majority of fact gathering comes from interviewing. Inquiry, question development and delivery, structured interviewing and aware and active listening matter a lot here. Never lead an interview in case you are building a case for a theory or ‘pet’ view that you have. Remain impartial at all times.

    It is important to be empathetic enough to be good at relating to people and getting them to open up when doing structured interviewing and active listening; if you are too proud or arrogant you can forget interviewing as a method of gathering data because it’s unlikely anyone will open up to you enough, and this will seriously impact your ability to perform reviews and audits in any meaningful manner.

    People will be people in the interviews: they will be emotive, some may be reserved, stoic, cynical even, some will care, some won’t, a few may be objective, many are wittingly or unwittingly subjective, and all will have opinions.

    Remember interviewing is the no.1 manner in which good quality data gathering is done for system, project and programme reviews and audits, becoming fluent in performing interviews and capturing the data thereof is key to performing good reviews.

    Do not lead the data, nor start to analyse until a good body of data is gathered. Often once facts have been gathered and started to be analysed more information may be required to perform a good quality diagnosis. Be prepared to ask lots of questions and be prepared to meet people who don’t want to answer you. Document everything.

  3. Result(s)This is where you will be relating facts into results; although some analysis and thought will have been done considering which information to gather and how, much of the real analysis ‘foot work’ starts here. This section is where you relate the information so far presented and relate it to issues and problems that the client is experiencing. Hopefully you should now have information gathered and documented in the ‘fact(s)’ section which is causing or could be causing the problems that the client is exhibiting. It is likely that you will be sorting facts and the problems that they are associated with into a basic set of categorisations (and the next article in the series deals with those categories).

    A simple example result may be that a defined problem might be “the web server keeps falling over, we don’t know why”, whilst the related fact may be that “patches were not applied”, after more investigation it would probably be fair to link the two together thus “a result of not applying the appropriate patches leads to the web servers being unstable”. The reason you shouldn’t jump the gun and stop with the first thing you come across is that it may not be the root cause, it could be a contributing cause or even unrelated, the good reviewer is appropriately thorough, without needlessly wasteful of clients time, money or resources.

    An example of a conclusion might be “without implementing and maintaining change control the project will continue to move out of control and will be increasingly difficult to deliver to time and budget, never mind delivering the contractually required document deliverables”.

    If the facts and results do not map to the original issue for which the exercise was commissioned, you would need to consider gathering more data which is more related to the original problem and re-iteratively gathering more information, alternately perhaps testing the validity of the original problem description and politely questioning the original area you were asked to review with the sponsor of the review (secure a meeting and let them know of the concerns and issues you are having). Document any disparity between the originally identified problems, the facts gathered and the results given here.

  4. Conclusion(s)Defining conclusions is where you look at the Facts and Results and conclude what will happen if the situation continues. This is where you make rational predictions on a future state, suggesting what problems might occur in the future if no action (or what planned action) is taken. It would be dismissive to say that this is where any ‘scaremongering’ occurs, but it is important to inform, and, possibly even, warn the client about further problems and issues that they might experience if the situation remains unchecked.

    It is important that your conclusions address the original problem and although you may like to address any additional problems which have been drawn out during the review it is not imperative to do so; however I almost always do and this is because I feel an obligation to the client and I want to demonstrate my delivery focus too, you however may not find this something you have time, or want, to do.

    Again this will probably be a short section, and although you well may have been creative before, this and the next section is where your good ideas need to start to be. You need to ensure that you are not too fanciful, and personally I prefer not to be seen to be influencing any particular recommendation by ‘weighting’ any possible future state too negatively however I have seen a lot of of reviews which have lacked impartiality over the years.

    If things are bad you must be honest and deliver the difficult news; whatever you do do not attempt to ‘sugar-coat’ the news and detract from the important information and messages you are delivering to the business; although I heavily recommend that you ensure that you inform your sponsor verbally early on so as to ensure you do not deliver any surprises which could have a possible negative effect and lose or diminish their support.

  5. Recommendation(s)This is where you make suggestions in terms of trying to improve the situation; deliver recommendations which relate to the facts, results and conclusions, and the original problem. If other problems have come to light during the review and you have included them as part of the overall review then you should include recommendations which address those problems as well.

    Making recommendations could well be seen as being the easy part to an experienced ‘expert’ with a certain field, and it is always attractive to the inexperienced reviewer to dive in with recommendations before proper analysis has been completed (i.e. we’ve found these facts, therefore because the last project had a similar issue and we fixed it by doing X, Y and Z, we will try X, Y and Z here). This behaviour will likely lead to either the wrong problem being fixed, or worsening the current situation, all of which waste the clients time, money and resources.

    With recommendations I like to remember the ‘pareto principle’ (the “80-20 rule”), in that your principal recommendations should by mindful of this and have significant impact on addressing the problem space originally described by the client. Minor recommendations are all well and good, but if they don’t “fix” the problem in the mind of the client it’s unlikely that you will be being asked to review for them again or that your recommendations are implemented at all.

    Above all recommendation are given so as to improve a situation, not to push any personal agenda, and again it is key to be impartial and objective.

The biggest problem you will likely have in using a framework like this, or any other, is early on you will likely have content in the following or proceeding section to the one it should be in, as you become more familiar with the framework and more experienced at doing reviews and audits this should improve.

Also do not imagine that the only place that you bring value is in the ‘Recommendation(s)’, this is grossly incorrect, because the client may well have not gathered the data you have, analysed it in that same way, nor come to the same conclusions. Your work ultimately will improve their understanding of a situation and allow them to plan accordingly, and this is the genuine value.

Of course a good review document will contain more than the above, probably references, appendices, document control, etc., however the above is the absolute core of a good review in my opinion and experience. If you find yourself arguing with your co-reviewers about the document version control table you are way off the mark, because fundamentally the quality of the review is paramount as well as the effect it brings (hopefully a resolution to the issues for which it was commissioned).

My friend, Chris Loughran, of Deloitte, use a framework even more stripped down and ‘lean’ than this, delineating into (1) gather facts, (2) relate results, and (3) make conclusions, which is certainly punchier and easier to explain in short order to your typical senior executive or CxO who has very limited time. But of course Chris is one of the leading Business and Technology Consultants in the UK, so this is to be expected and he is highly effective using this approach. Personally, as I’ve written about in this article, I prefer to document the (perceived) problem and to ensure recommendations are distinct from conclusions.

As usual, I hope you have enjoyed the article despite it being a lot larger than I hoped, and to mention that the next one is looking at the categories of reasons why projects and programmes fail (although I’ve just decided to deliver and have subsequently written a short article documenting an example of the above review and audit framework too).

Reviewing, auditing and rescuing failing projects and programmes best practice

One of the things I’ve done rather too much of is be asked to review failing projects, programmes and build-outs for customers, clients and partners, and come up with solutions and recommendations to help resolve these problems, which is often followed in short order by being asked to help rescue them (often leading to Sun helping them too).

And over the years I’ve built up a fairly large body of case studies and examples, which when I make the material a little more anonymous and write up I will share, but for now I’ve put together a couple of articles that use this experience.

First one to follow this leader is an article on a project review / programme audit framework which is a simple, highly effective and yet generic method for setting out reviews.

Secondly is a piece on why project fail, at least the five macro-level reasons why projects fail, within which I’ve found all programme problems seem to fall. This is of an appropriately high level to be useful to those who review and audit problem implementations and systems, don’t expect to find items such as “it was a triple indirected pointer to a function in C / C++ that ended up at the wrong memory location”.

Anyway really hope you enjoy the articles, because, well frankly, there is a lot of time, effort, experience, and failing projects knowledge boiled down into these.

Hosting a BCS Enterprise Architecture event on EA Tools tomorrow in Manchester

Tomorrow evening I’m going to be hosting a BCS Enterprise Architecture (EA) speciality group (SG) event looking at EA tools in Manchester.

Details for the event:

Date / Time: Friday the 17th of July, 2009 / 17:45 for 18:00, expected to finish at 19:30

Location: Room E0.05, John Dalton Building, Manchester Metropolitan University, Chester Street, Manchester M1 5GD

More information and registration over at the BCS EA AG website page for the event: http://www.ea.bcs.org/eventbooking/showevent.php?eventid=esg0906

Event synopsis from the BCS EA SG:

The focus of enterprise modelling is now shifting away from purely technical and system aspects and becoming more holistic, thereby necessitating the use of comprehensive modelling tools to analyse and optimise the portfolio of business strategies, organisational structures, business processes, information flows, and services. Organisations would be ill advised to proceed with Enterprise Architecture without utilising a modelling toolset able to meet all the requirements. A central repository is vital to provide a common information source for everyone involved, also important is the ability to base the process on a framework and customise the models to fit each organisations own situation. The presentation will cover Enterprise Architecture tool evolution, key tool capabilities, and market overview.

We have secured Mark Blowers as the nights speaker; Mark has over twenty years experience in the IT industry, employed by end-users and software houses, working in a number of roles, from analyst/programmer to project manager and account manager, in the manufacturing, retail, and Independent Software Vendor (ISV) sectors. Mark joined Butler Group in August 2000, and is Enterprise Architectures Practice Director. He has worked on a number of strategic and architectural themes over the last few years, including Enterprise Architecture, IT Value Management, Enterprise Communications, and Mobility. Mark has been widely quoted in the press, including the Financial Times, Guardian, Computing, Computer Weekly, Internet news sites, and other trade magazines.

This should be an interesting and informative event, so I’m looking forward to being there already.

Cloud Computing reading recommendations from Jim Baty

Here’s a few Cloud Computing reading recommendations from Jim Baty, Senior Vice President and Chief Architect for Global Sales and Services. I’ve had these for a couple of months now but I thought I’d post them anyway as they are well worth a read.

some reading that folks are talking about

clouds from Berkeley / Patterson

http://www.eecs.berkeley.edu/Pubs/TechRpts/2009/EECS-2009-28.pdf

data intensive supercomputing

http://www.cs.cmu.edu/~bryant/pubdir/cmu-cs-07-128.pdf

implementation comparison of GAE & AWS

http://www.slideshare.net/mastermark/fowa-miami-09-cloud-computing-workshop-1059049

Itex and Sun thought leadership event ‘A Computing Revolution: Why Cloud Computing Changes Everything’ in Guernsey on Tuesday the 2nd of June, 2009

ItexSunEvent.png

So whilst a number of my colleagues, friends and peers at Sun are off enjoying JavaOne, the no.1 Java event of the year, and CommunityOne West, I’m going to be in Guernsey, where I’m keynoting at the Itex / Sun Thought Leadership event “A Computing Revolution: Why Cloud Computing Changes Everything“.

During the event we’ll be looking to cover the following topics:

  • What is Cloud Computing and why does it matter?
  • Will it benefit my department or business and how will it impact the IT function?
  • What are the applications of Cloud Computing, today and in the future?
  • What will it mean for small niche jurisdictions such as Guernsey?
  • What is the role of Government in facilitating the new computing environment?

I’d just like to say ‘Many Thanks’ to everyone at Itex who helped organise this event, especially Daniel Fitton, Richard Parker and Chris Eaton, and to Paul Tarantino and Greg Roberts, of Sun UK’s Internet and Web2.0 team, who originally put me forward as guest speaker.

Details for the event are:

  • Date: Tuesday the 2nd of June, 2009
  • Time: 8:15am to 9:00am for Breakfast, 9:00am to 10:30am for the event
  • Location: Old Government House, St Peter Port, Guernsey
  • Registration: To reserve a place email events@itexoffshore.com or call 01481 710881

Itex have created a flyer for the event, which is available here (in PDF format). Event page is: http://www.itexoffshore.com/NewsAndEvents/Events/May+2009/Cloud_May09.htm

I really shouldn’t say be saying this, as JavaOne is big news in the IT Industry, especially at Sun, and has an incredibly exciting line up of speakers and agenda this year, but I’m looking forward to being in Guernsey more.

Frankly I’ve been to the States a fair amount with work and conferences but I’ve never been to Guernsey yet; I’m really looking forward to going and think I’ll have a great time too. Expect to see slides, write up and photos sometime next week.

Shock! New report says IT Management don’t care about Power Efficiency

Shockingly the latest report from Forrester Research effectively ends up telling us exactly what we all know already; that the majority of CIOs, CTOs, and other IT leadership and operations management, are not interested in power saving.

As reported recently by The Register in the article “Study finds IT heads not interested in power saving” (available here: http://www.theregister.co.uk/2009/04/30/pc_power_saving/) which confirms what most of us in the IT industry know to be true, in that in the majority of cases because power consumption comes under the remit of Facilities Management in most organisations the IT department is not responsible for paying for Power Consumed (whether that be for compute, storage and network infrastructure itself, or the cooling equipment that is required to maintain that infrastructure either) and so has no reason to be concerned about the size of the companies power bills (or the effect of poor IT power efficiencies on those bills).

Also in almost all companies the Facilities Management department is much larger, and has a much larger budget, than the IT department; easily often in the magnitude of ten times that of the IT department (in some organisations the IT department is part of the Facilities department, and we most often encounter this model when the organisation in question sees IT purely as organisational ‘infrastructure’ and tends not to see IT as a means to deliver competitive advantage).

Encouraging IT management to be concerned about power efficiency is still highly problematic whilst the IT department is not accountable for managing that Cap-Ex spend, although things are getting better, albeit slowly. Day to day I see large numbers of IT departments and management thereof being set targets for power savings, however I infrequently see any genuine penalties or incentives that ensure these targets are even remotely met (in most cases I see IT departments focus being that of maintaining business critical systems, especially during processing runs, whilst still attempting to build out new functionality at the same time, how little things have really changed).

What constantly amazes me are the number of organisations planning, and determined to, build out new data centre facilities, even now during the downturn. Many of these organisations would be much more sensible to look at refreshing there existing infrastructure, reducing server footprint, getting better energy efficiency and performance, as long as the risk impact and analysis of risk is low, and possibly even reducing their data centre footprint, but that would mean shrinking peoples corporate ‘power bases’ and personal ’empires’ and so often receives a lack of genuine support.

Frankly this would become an important topic if those responsible for the facilities budget where also responsible for the IT budget, but this is rarely the case; IT usually reports to Operations (which may also contain facilities), Finance, or occasionally even the the Main Board or Marketing (including Sales), followed rather infrequently by facilities (this becomes more complex when looking at the IT departments remit, and whether they have significant influence, or control, over the application development team and the business analysts from the profit generating business units).

The most obvious answer would be to get IT and Facilities to work much more closely together, and at least be set joint targets, which are ‘SMART’ (stands for “Specific, Measurable, Achievable, Relevant, Time-framed”). The other that I’ve heard becoming more popular recently has been to redirect Facilities budgets to IT departments for them to run technology refresh programmes, with a recent example looking at an unprecedented 10% of Facilities budget being transferred to IT, nearly doubling that IT departments budget for the year.

Personally I don’t think this will be addressed well in the short term, but I’m hopeful that using budget earmarked for Facilities for Technology Refresh, and planning facilities reductions becomes a more widely recognised and sensible approach to help drive down the amount of energy consumed by the technology at use within enterprises, because, frankly, something needs to be done to reduce enterprise consumption of power and space resources.

Links for this article:

‘Exploration of Cloud Computing’ at the Birmingham BCS Branch AGM this coming Monday; looking for new Committee members

Interested in Computing in Birmingham and the West Midlands? Then come along and join us at the BCS Birmingham Branch Annual General Meeting (AGM) this coming Monday, where we are looking for members to come forward to join the Branch Committee.

After the AGM itself I’ll be doing a presentation called “An Exploration of Cloud Computing” with the following synopsis:

An exploration of Cloud Computing looking at an overview of the subject of and some of the current common definitions available. Looking at the current state of the Cloud Computing market place and Cloud Vendors, what is actually being sold to people. Will also look at the different types of clouds, the differing approaches to engaging with cloud providers, the business models, impact on Business, and how Businesses can exploit the ‘Cloud’.

Answers to key Cloud Computing questions I hope to address include:

  • What’s Cloud Computing?
  • What’s different to what we’ve seen before?
  • What’s driving Cloud Computing adoption?
  • What types of Cloud are there?
  • How can I engage with them and use in my Business?
  • What’s the overview of the Cloud Computing marketplace now?
  • How is Cloud Computing likely to change?

A number of the members of the Birmingham Committee will be standing down at the AGM so we are looking for volunteers to join the Committee to take part in planning our activities for the 2009-10 session. If you are interested in joining the Committee please contact John Chinn, Branch Secretary, at john.chinn@manchester.ac.uk or you can come forward at the AGM itself.

Details for the event are:

  • Date: Monday the 18th of May, 2009
  • Time: AGM at 6pm for 6.30pm, Presentation at 7pm
  • Location: Trophy Suite, Tally Ho Sports & Conference Centre, Pershore Road, Birmingham B5 7RN
  • Cost: Free, Presentation open to all (including non-members of BCS), no registration required although we would prefer that you contact the Branch Secretary, John Chinn, at john.chinn@manchester.ac.uk or 0161 306 3733, so that we can advise the caterers of the correct numbers for the buffet.

Official BCS Birmingham Branch AGM and “An Exploration of Cloud Computing” page: http://birmingham.bcs.org/agm2009.htm

Very much hope that we will see you at the Branch AGM, and even better if your interested in being involved with the Committee.

Links for this article:

Enterprise Architecture Case Studies presentation on Friday the 8th of May in Aberystwyth

This Friday I’ll be presenting on the topic of ‘Enterprise Architecture Case Studies’ in Aberystwyth, in an event organised and hosted by the South Wales branch of the BCS.

For more information the event is advertised here with the BCS. The core details are:

  • Date: 8 May 2009
  • Time: 17:00 Refreshments / 18:00 Start
  • Location: The finger buffet is in the foyer of the Computer Science Building and the talk itself will be in Lecture Theatre `A’ in the Physical Sciences Building, both on the Penglais Campus, Aberystwyth University, Aberystwyth.
  • Cost: Free, open to all (including non-members of the BCS or IET), no registration required.

Here’s what I generally say as an overview of this talk:

The case studies presented explore my experiences with Enterprise Architecture in three major customer engagements. They include an Enterprise Architecture team which led its company into a £70+ million ‘pitfall’; the use of Enterprise Architecture to define a Service Oriented Architecture; and an example of how much Enterprise Architecture is about achieving the proper governance model.

Key takeaways:

  • Enterprise Architecture best practices drawn from multiple engagements.
  • How to use good governance to avoid and limit the ‘Ivory Tower’ syndrome.
  • How to combine Enterprise Architecture and Service Oriented Architecture to deliver sustainable Transformation.

Given the current downturn I’ll also go into some of the issues facing EA programmes due to the credit crunch and what can be done to ensure that they continue to receive executive sponsorship and funding.

Happy to answer any and all questions; please consider that I’ll be attempting to condense three major and very large scale Enterprise Architecture case studies into a talk lasting an hour and a half or so, therefore I will definitely be around to speak with afterwards. ¨C13C

‘Many Thanks’ to Fred Long (of Aberystwyth University) for organising and co-ordinating this event and for Clive King (of Sun) for initially brokering the relationship.

Links to the BCS page for the event: ¨C14C

¨C15C ¨C16C¨C17C

Links for this article: